| 34. |
PT Citra Kusuma Perdana, Sangatta, East Kalimantan, Indonesia 2011 |
Consultancy Services |
Consultancy Services for Electrical Power System Study of 3X18 MW Coal Fired Steam Power Plant. |
| 33. |
KNPC Mina Abdulla Refinery, Eartha / Kremenco. 2011 |
Consultancy Services |
Engineering consultancy work for selection of Current Transformers for the Differential Protection of Recycle Gas Compressor Motor. |
| 32. |
Shadeed Iron & Steel LLC (Jindal Shadeed), Oman 2011 |
System Studies |
Relay Setting & Relay Coordination study |
| 31. |
Alghanim International General Trading & Contracting Co. W.L.L., Kuwait 2011 |
Consultancy Services |
Investigation for the tripping of 131.13 KVA ESP Transformers at KNPC, Kuwait, MAA Refinery. |
| 30. |
Punj Lloyd PTE Ltd. / PT. Makmur Sejahtera Wisesa (MSW), Indonesia 2010 |
Consultancy Services |
Providing Electrical Engineering Consultancy Services for 2 X 30 MW, Coal fired Power Plant project at Tanjung - Tabalong, Indonesia.
|
| 29. |
PT. Indorama Synthetics Tbk, CPP, Indonesia 2009 |
Testing and Commissioning and Condition Monitoring |
a) Condition Monitoring Testing for Generator, Exciter and Generator Transformer. b) Testing of Protective Relays, CTs, PTs, Switch Gear and Schemes. |
| 28. |
Abu Dhabi Oil Refining Company, Takreer 2009 |
System Studies |
Relay Setting, Relay Co-ordination study for electrical system of Abu Dhabi Oil Refinery, Ruwais Sulphur Expansion Phase III project. |
|
27.
|
PT. Indorama Synthetics Tbk, CPP, Indonesia 2009 |
Testing and Commissioning |
Site visit and summarizing Analysis of Major Faults in Indorama Power Plant. |
| 26. |
KAMAL Engineering Consultants, Dubai 2008 |
System Studies |
Relay Setting, Relay Co-ordination and Harmonic Analysis for District Cooling Plant Project. |
| 25. |
PT. Indorama Synthetics Tbk, CPP, Indonesia 2008 |
Consultancy Services |
Site visits and Occurrence Review. |
|
24.
|
PT. Indorama Synthetics Tbk, CPP, Indonesia 2008 |
Testing and Commissioning |
a) Testing of Protective Relays and Schemes for Unit-1 & Unit-2. b) Condition Monitoring Testing of 30 MW, Unit-I and 2 x 10 MVA, HT Auxiliary Transformer. c) Testing and Commissioning of Grid Islanding and Load Shedding Scheme. |
|
23.
|
PT. Indorama Synthetics Tbk, Polyester Division, Indonesia 2008 |
System Studies |
Our Scope of work includes the following, a) Load flow study. b) Short circuit study. c) Relay setting and relay co-ordination study. |
| 22. |
CHEMAF S.P.R.L., (Republic of Congo), Africa 2008 |
System Studies |
Feasibility study of Load Flow, Short Circuit and Relay Co-ordination of existing Plant electrical distribution system and upgrading the same with upcoming new requirements / projects. |
|
21.
|
Hajar Trading & Technical Services, Kingdom of Bahrain 2007 |
Testing and Commissioning |
Modification and Overhauling of 11 kV Medinsha VCB’s for Bahrain MEW. This includes carrying out, a) Wiring modification of auxiliary switches for Meidensha Make VCB’s, Type VFT-12 and b) Modification to replace existing auxiliary contact (Finger contacts) block. |
|
20.
|
PT Indorama Synthetic Tbk, CPP, Indonesia 2007 |
System Studies |
Power System Study for the electrical system including : a) Short circuit study. b) Relay Setting and Co-ordination of 30 x 2 MW Power Plant. c) Unit protection settings d) Transient Stability Studies. e) Design Engineering of Grid Islanding Scheme (GIS) and Load Shedding Scheme (LSS). |
| 19. |
Emirates
Trading Agency L.L.C., Associated Constructions & Investments Co.,
L.L.C., U.A.E. 2007 |
Consultancy Services | Deputation of Senior Executive for providing Consulting Services in connection with ALBA - RST Failure. |
| 18. |
SAUDI BASIC
INDUSTRIES CORP. (SABIC), Saudi Arabia 2006 |
Detail Engineering |
Detail
engineering for upgradation of existing UPS system for IT Department.
This
includes, a)
Study / evaluate existing UPS power system network and b)
Preparation of technical specifications, drawings for the new c)
Preparation of drawings for layout of equipment, cable tray d) Preparation of specifications for engineering package. |
| 17. |
JOINT
OPERATIONS, Wafra,
Kuwait 2005 |
System Studies | Relay co-ordination study for electrical system of Water Disposal Phase III Drain Recycling facility. |
|
16.
|
JOINT OPERATIONS, Wafra, Kuwait 2005 |
System Studies |
Electrical
system study of Wafra electrical system including, Short circuit study. a)
Relay setting and co-ordination. b)
Load flow studies and steady state voltage drop studies. Calculate Sag and Tension for 34.5 kV and 13.8 kV transmission lines. |
|
15
|
Heavy
Engineering Industries Shipbuilding Co. (K.S.C), 2005 |
Testing and Commissioning | Testing and Commissioning of 3.3 kV feeder for new 3.3 kV / 460 V Transformer of Sludge Handling Plant |
| 14. |
Kuwait National Petroleum Company Kuwait 2005 |
System Study |
System
study for Mina Abdulla Refinery electrical distribution system
including, a)
Short circuit study. b)
Relay setting and co-ordination. c) Unit protection settings of synchronous motor, synchronous |
|
13.
|
Kuwait National Petroleum Company Kuwait 2005 |
Consultancy services | Consultancy
services during project execution of revamping of Frequency Converter
system. This includes review of documents prepared by vendors and advise
KNPC on various detail engineering issues related to this project. |
| 12. |
PT. INDO
BHARAT RAYON LTD., Indonesia 2004 |
System Studies |
Scope
Of Work includes, a)
Rationalization of Electrical Power Distribution. b)
Detail engineering of Power evacuation for new 2 x 10.8MW CPP c)
Rationalization of Power Source Grounding System. d)
Carryout Transient stability studies, load flow study, short circuit e)
Design and engineering of Grid Islanding scheme and post |
| 11. |
Heavy
Engineering Industries Shipbuilding Co. (K.S.C), 2004 |
System Study | Study of Relay setting and relay co-ordination for the electrical system of Sludge Handling Plant |
|
10.
|
Kuwait National Petroleum Company Kuwait 2004 |
System Study | Relay setting and Co-ordination study for electrical system of Sludge handling plant. |
| 9. |
FIji Electricity Authority, FEA Fiji 2003 |
System Study | Study of voltage profile, VAR compensation, stability and Relay setting and relay co-ordination for the Wainekasou and Wailoa sub-station electrical system. |
|
8.
|
Kuwait National Petroleum Company Kuwait 2003 |
System Study | Study of current collector and speed variation technique and suggest improvement for bridge crane unit 47. |
|
7.
|
Kuwait National Petroleum Company Kuwait 2003 |
System Study | Study of protection relay co-ordination and readjustment of protective relay setting at MAB refinery. |
| 6. |
Kuwait National Petroleum Company Kuwait 2002 |
Consultancy Services |
Consultancy
Services for Revamp of Frequency Conversion System for Reliability. The
scope of work was, a) Evaluation of Critical Clearing Time for faults in utility and
revision b)
Up gradation of Protection logic for Synchronous Motor – c)
Detail engineering for implementation of suggested schemes for |
| 5. |
Petrochemical Industries Corporation Kuwait. 2002 |
System Study | Consultancy services for Electrical system modification. |
| 4. |
Kuwait Oil Company Kuwait 2002 |
System Study |
Scope
of work for the system study includes, a)
Carry out System Fault analysis with new machines to check the b)
Review of Integrated Protection Scheme for H.T. Motors. c) Determine the adequacy of existing generator ratings. |
| 3. |
Kuwait Oil Company Kuwait 2002 |
Consultancy |
Cable sizing calculation for new crude export pipeline from NK to CMM |
| 2. |
TCL INDUSTRIES (MALAYSIA) SDN BHD, Malaysia 1998 |
Power Plant | 7 MW steam based power plant, detail engineering, Testing & Commissioning and complete system study. |
| 1. |
P.T. Polysindo Eka Perkasa Indonesia 1998 |
System Study | Working of complete electrical system, short circuit, load flow, stability and protective relay settings and co-ordination on software. |