CURRENT UPDATES
|
|
SR. NO. |
CLIENTS |
TYPE OF JOB |
|
11.0 |
Century Enka Ltd.,
Pune |
Scope of work includes carrying out harmonic measurement at various location of electrical system. |
|
10.0 |
Deepak Fertilizers
& Petrochemical Corporation Ltd.,
Taloja |
Testing, Retrofitting and Commissioning of Siemens Make feeder protection relay, |
|
9.0 |
Vadinar Power Company Ltd.
(Essar Project - JamNagar) |
Testing and Commissioning of, a. 92 MW, 105 MW, 130 MW STG, its control and relay panels. b. 63.5 MVA, 2x140 MVA, 2x27.5 MVA Power Transformer and its control and relay panels. c. 5 nos. 3.2 MW Motors. |
|
8.0 |
Wartsila India Limited |
Testing of Generator Protection Relays of 2x30 MW unit and Relays of 2x45 MVA Generator Transformers. |
|
7.0 |
Atul Limited,
Valsad |
Testing of Protection Relays and Schemes of 66 kV Grid Islanding Panel. |
|
6.0 |
Ambuja Cement Limited,
Bhatapara |
Testing and recommissioning of2x15 MW and 33 MV STG. The scope of work includes, a. Testing of current transformer/ Potential transformer. b. Testing of Generator Protection Relays. c. Modifying the PSL logic in MICOM P343 relays and also the class ABC trip logics. d. Carrying out control circuit testing. |
|
5.0 |
Ultratech Cement
Limited, Kovaya |
Testing of ABB make REL 670 line distance protection relay and ABB make RED 670 relay line differential protection relay |
|
4.0 |
ACC, Kymore |
Testing and commissioning of ABB make REG 670 relay. The scope of work involves, a. Testing of Generator Protection Relays. b. Creating the logic as per existing wiring in the relay. c. Adopting the Generator Relay settings as per recommendations. |
|
3.0 |
Ambuja Cement Ltd., Lakheri |
Testing of Protection Relays of Electrical system. |
|
2.0 |
Ambuja Cement Ltd., Kodinar |
Testing of Protection Relays of Electrical system. |
|
1.0 |
Essar Projects India
Ltd., Salayaa |
Testing and Commissioning of 2 x 600
MW Power Plant Scope of work includes, a. Testing of Current
Transformer / Potential Transformer. b. Testing of Protective Relays. c. Testing of current
operated Differential Protection Scheme. d. Testing of Auto
Transfer scheme. |
Update : 27.01.12